After carrying out works at the practice owner’s private residence Mason & Mason Construction were invited to tender for phase 1 and 2 works at the very busy NHS and private Dental Surgery located in Sneyd Green, Stoke on Trent.

As a busy practice with Four separate working surgeries it was imperative that there was no surgery closure or loss of surgery time. After devising a suitable strategy works commenced “out of hours”
From the close of busines hours in the afternoon the team would then commence the “night shift” often working until 4am in the morning to ensure the practice was safe, clean and sanitised ready for patients the following day.

Mason & Mason Construction is happy to confirm that NO business hours were lost during the Phase 1 works and no practice closure occurred. We now look forward to Phase 2 works due to start early Novemember which will see a second storey extension added to the practice.

Read more about the surgery expansion programme through the local press coverage:
All smiles for 2000 more NHS Dental Patients

 Phase one works included

  • Remove existing surgery cabinetry and supply and fix new cabinetry and worksurfaces
  • Removal of internal loadbearing wall to enlarge reception area
  • Construct new boundary wall
  • Carry out car park permanent markings and form disabled car parking bay
  • Upgrade and install new emergency lighting and fire alarm system
  • Carry out a full redectoration of circulation areas to assist the visually impaired in accordance with Part M of the building regulations
  • remove internal lead lined partition within private surgery